On new work ensure RESIBLOCK F.R.I is installed concurrent with
the installation of the kiln dried sand on a daily basis. DO NOT
WAIT UNTIL THE CONSTRUCTION IS COMPLETED BEFORE APPLYING THE SEALER.
 |
| CONTAINER SIZES |
RESIBLOCK F.R.I is available in 25 litre containers.
 |
| COVERAGE |
First coat 1.8 m2/litre
Second coat 3.0 m2/litre
Coverage can vary depending on type of
paver and depth of joint penetration. Accurate application
rates are essential to achieve
full technical benefits.
 |
| SUBSTRATE/SURFACE CONDITIONS |
The surface should be clean and free from oil, algae, dust and
traffic film. Temperature must be above 3o C and below 30o C. Application
outside of this temperature range may be possible, but please refer
to our technical department prior to application. Substrate and
jointing sand must be dry. Jointing sand that contains moisture
will prevent bonding and stabilisation of joints. Do not use if
rainfall is forecast within 8 hours of project completion.
Ensure that the sand does not protrude from the base of the chamfers,
if the sand is not properly removed, it may be picked up by the
application tools.
 |
| PREPARATION |
On new work all that is usually required is a good sweep with
a stiff broom, however if the surface has become partially weathered
or contaminated, low pressure wash to remove all debris. For very
soiled areas or excessive weed infestation – see section "Refurbishment".
For successful use, optimum performance and maximum penetration
ensure joints are well filled to the bottom of the chamfers with
clean, compacted kiln-dried sand, complying with BS 6717 or equivalent.
(See notes on substrate conditions re sand removal and moisture).
Coarse jointing sand will significantly reduce spread rates.
RESIBLOCK F.R.I must be installed immediately following
final compaction, however where this is not possible, or where
there
is an anticipated delay, paver joints should not be filled with
kiln dried sand. This would allow final joint filling on the
same day that the surface is to be sealed. The jointing sand thereby
being completely dry, allowing for optimum absorption of RESIBLOCK F.R.I
Application to poorly prepared pavers particularly in respect
of dampness can result in inadequate joint penetration, paver adhesion
and discoloration.
 |
| REFURBISHMENT |
Inevitably existing constructions will have severe weed infestation
and traffic film build-up, which would need to be dealt with in
the following manner.
The entire paved area is treated with commercial weed killer six
weeks prior to cleaning. If necessary this process is repeated
three weeks prior to cleaning (usually required if significant
rainfall was apparent after the first application). Upon installation
of traffic management systems, operatives would manually remove
all dead weed and grass growth. (This work needs to be meticulous.)
The surface would then be pressure washed using a traffic film
remover if necessary. At the end of the process once again the
entire area would be treated with a commercial weed killer.
At this stage localised repairs to damaged pavers would normally
take place. As soon as the substrate and jointing sand was dry
(subject to weather conditions) application of the RESIBLOCK F.R.I sealer
as detailed below can commence.
NB It should be noted that when contractors quote for this work
they would normally expect the following two items to be supplied
and paid for by the client:
(a) Traffic management.
(b) Supply and connection to water hydrant including standpipe
key etc.
 |
| EQUIPMENT |
RESI-ROLLERS and RESI-SCUTTLES.
 |
| METHOD OF APPLICATION |
RESIBLOCK F.R.I can be used straight from the container
without thinning or addition of a reactive agent; it must not be
diluted.
However being aliphatic based, it is temperature sensitive and
as such if stored at temperatures below 10degrees C, the polymer
may tend to settle out of the solvent, as such ensure contents
of container
are thoroughly mixed.
An area approximately 1m by 8m should be marked out and 5 litres
of F.R.I applied by RESI-ROLLER. The material should be applied
using the roller horizontally to the kerb. Sufficient material
should be worked into the joints so it will initially fill the
chamfers (ultimately to be completely absorbed). Surplus F.R.I
should be rolled off the surface and into the joints to ensure
maximum performance.
When the first coat has become palm-print dry a second coat is
applied to the entire area, this time roller application should
be vertical to the embankment. Using the roller in opposite directions
in this manner will ensure that the entire area is properly covered.
 |
| METHOD OF APPLICATION FOR REFURBISHMENT |
RESIBLOCK F.R.I is applied in the same manner as indicated in
paragraphs 1, 2 & 3 above. However as the cleaning process
would have inevitably removed the majority of the reflective Ballotini
beaded surface, it will be necessary to use 'RESIBLOCK F.R.I HV'
for the second coat. Being a high viscosity and hence more thixotropic
material, it would allow a coating of Ballotini beads to be added
to the majority of the white paved area, this is done simply using
the broadcast method, whilst the F.R.I HV is still wet.
 |
| CURING PERIOD |
Rapid initial cure will take place depending on ambient temperature,
humidity and block porosity; 1-4 hours can be expected. Immediately
the surface is dry the paved area can be opened to traffic but
full catalytic cure must be allowed to take place (72 hours) if
the pavers may be susceptible to vehicle overrun.
 |
| STORAGE |
Containers should be stored under cover and be protected from
extremes of temperature. Partly used containers should not be stored.
Any remaining traces of material in used drums must be cured by
leaving the containers open; and in dry conditions, by putting
water into each container.
 |
| SHELF LIFE |
RESIBLOCK F.R.I (unopened containers), has a shelf life of 6
months.
 |
| CLEANING TOOLS AND EQUIPMENT |
RESIBLOCK F.R.I cures rapidly when exposed to atmospheric
moisture, to give a film that can only be removed with great difficulty.
For this reason it is recommended that all equipment be cleaned
immediately using RESICLEAN. Do not use other solvents as unknown
synergistic reactions may take place. Wash with water and detergent
afterwards. RESICLEAN is also effective in the removal of splashes
and spillages’ of uncured sealer
 |
| HEALTH AND SAFETY GUIDELINES |
PVC gloves and protective clothing/face shield must be worn, plus
use of a barrier cream on exposed areas of skin, as uncured RESIBLOCK
F.R.I may be considered a hazardous material.
No smoking or naked flames be allowed, as RESIBLOCK F.R.I is
flammable. Ensure area to be treated is well ventilated. If public
access is allowed, erect No Smoking signs and site fire extinguishers
A mask of the recommended type is essential when using a paintbrush,
working close to the surface or internally. Sabre or Martindale
is recommended.
Do not apply RESIBLOCK F.R.I in the presence of foodstuffs.
Once fully cured it can be considered innocuous. Do not clean hands
with RESICLEAN as solvents tend to de-fat skin that can lead to
dermatological problems.
Do not return unused material to original containers. DO NOT RESEAL
or store partly used kegs. Material so stored may have poor adhesion
and Carbon Dioxide may generate and put the drum under pressure,
which might rupture the drum. Furthermore, partial or total solidification
of the sealant may occur.
Please refer to Resiblock Limited's current Material Data Sheets
for the latest and comprehensive information on this section
|